TCO Future Growth Project

TCO Future Growth Project
February 28, 2020
Gorgon Stage 2
February 28, 2020

TCO Future Growth Project

Client Schneider Electric (France)
End User Tengizchevroil (TCO – Chevron / ExxonMobil JV)
Project Owner PJV - Projects Joint Venture (FLUOR, United Kingdom)
Start Date 31 Jul 16
Completion 14 Aug 19
Location Fabrication : WEI – Batam Indonesia
Delivered To: Tengiz ,Kazakhstan

Schneider Electric France awarded Wasco a contract for the supply of 7 off 10KV Substations weighing about an average weight of 850 mT. The substations were designed and constructed to Eurasian Customs Union (EAC standards) and for extreme weather conditions ( -40 ⁰C to +40 ⁰C). It was a proud moment in Wasco's history to have delivered all seven substations meeting the "Target Zero" goals, including working over 3 million manhours safely without LTI. The scope of work included: Engineering, Partial Procurement, Construction & Assembly Work, Painting Work, Interconnecting cabling, Pre Commissioning, Commissioning, Architectural Work, Installation of free issue equipment, F&G System, MC and Documentation