NCS5

The Future Growth Project (FGP), Kazakhstan
February 28, 2020
Sao Vang and Dai Nguyet (SVDN) Development Project for PTSC, Vietnam
February 28, 2020

NCS5

Scope of Work Design, Supply, Installation of 120MMSCFD Compression Station
Capacity 120 MMSCFD

To install a full compression plant facility at NCS5 Site. WASCO was awarded this project and offered a solution which included the complete design, fabrication, installation and commissioning of the complete Gas Compression station. The activities involved laying out the facility plot plan and related safety studies), Detail Design of Equipment and vessels, Fabrication of all Equipment's, Civil Foundation (Piles and Raft) Design, Plant utilities, Installation, Commissioning and SAT.