Client | Schneider Electric Singapore (SES) |
---|---|
End User | Brunei LNG, Brunei |
Project Owner | Brunei LNG, Brunei |
Start Date | 13th Dec 2018 |
Completion | 15 Aug 2019 |
Location | Fabrication : WEI – Batam Indonesia Delivered To: Onshore Brunei |
Schneider Electric Singapore (SES) awarded the EPC contract for 1 x FAR building to Wasco in Dec 2018 with a very tight delivery schedule, FCA Wasco yard August 2019. Wasco scope included Engineering, Procurement, Fabrication, Weight Control, Equipment installation, HVAC system, Fire and Gas system, Coating, Mechanical Completion, Testing, Pre-Commissioning and all other things necessary to complete the construction of the FAR. Also included was a comprehensive set of documentation. The FAR installation is to be located in Onshore, Brunei. Wasco successfully completed the FAR on schedule and it was loaded out in 2019 by SES for delivery to the Brunei LNG Project, Brunei. The FAR was designed and fabricated to meet challenging stringent Brunei and Shell requirements, the Wasco team overcame some large hurdles, clocked more than 31,000 man hours without LTI and the FAR was delivered on time with no punch list.