Western Isles Development FPSO – Fine Filter Skid

GLNG Plant Project – Prefabricated Powerhouse and Electrical Equipment Package
September 1, 2014
Garagol Deniz Project
December 1, 2014

Western Isles Development FPSO – Fine Filter Skid

Client Veolia Water
End User Veolia Water
Project Owner Veolia Water
Start Date 8th Dec 2013
Completion 29 May 2014
Location Fabrication : WEI – Batam Indonesia
Delivered To: VEOLIA - Singapore

WASCO Engineering Technologies (WET) received PO from VWSW on 12 Dec 2013. For fabrication one complete package of Sea Water Fine Filter Skid completed with 3 units Pressure Vessel design and fabrication /installation onto skid as per client specification. Project Wasco internal KOM commenced on date 8th Dec 2013.

Scope of work includes :

  • Engineering (Receive & Submit)
  • Procurement (Receive & Submit)
  • Construction & Assembly Work
  • Installation & Commissioning
  • Interconnecting cabling
  • MC/ITR, Punch list, IFAT
  • Load Out, Export Clearance & Transportation
Project in progres contruction with curent cummulative manhours spents up to end of Jan 2014 = 637 manhours WITHOUT LOST TIME INJURIES