Western Isles Development FPSO – Fine Filter Skid

EVA-NMB Gas Delivery System (ENGDS) (JDA) Project
March 1, 2014
Wheatstone Ashburton West Pipeline Project
August 12, 2014

Western Isles Development FPSO – Fine Filter Skid

Client MODEC - Singapore
End User MODEC Offshore Production System Singapore PTE LTD
Project Owner Tullow Ghana Limited
Start Date 25th Jan 2014
Completion Load Out
1P = 26 Jan 2015, 7P = 11 Oct 2014, 8P = 25 Jan 2015
Location Fabrication : WEI – Batam Indonesia
Delivered To: Offshore Ghana, Africa

Modec Offshore Production System Pte Ltd has awarded Wasco Engineering Services Ltd, a contract for Partial Procurement, Prefabrication, fabrication, weight control, erection, equipment installation, coating, mechanical completion, testing, pre-commissioning and all other things necessary to complete the construction of the topsides modules and documentation of modules iInstallation on TEN FPSO is to be located in Offshore Ghana, Africa.

Scope of work includes :

  • Partial Procurement
  • Construction & Assembly Work
  • Painting Work
  • Interconnecting cabling
  • Pre Commissioning
  • Architectural Work
  • Piping Work
  • Installation of Available free issue equipment
  • F&G System
  • MC and Documentation
The total weight of prefabricate electrical house’s are 8785 Tons (Preliminary) Project 1st cutting will be held on 28 February 2014