TEN Development Project FPSO – Prefabricated Powerhouse Package

Presure Vessel Fabrication of Compressore Package
April 18, 2013
CAIRN – Manggala Polymer EOR Development Project 1st Call Out Order
December 26, 2013

TEN Development Project FPSO - Prefabricated Powerhouse Package

Client ABB Pte Ltd - Singapore
End User MODEC
Project Owner Tullow Ghana Ltd
Start Date 18th Dec 2013
Completion Load Out 14 Oct 2014
Location Fabrication : WEI – Batam Indonesia
Delivered To: MODEC - Singapore

ABB Pte Ltd has awarded Wasco Engineering Services Ltd, a contract for design supply of materials, construction, assembly, supply, inspection, testing, commissioning and documentation of E-House complete with Battery Room, Instrument Room, and VFD Room for Installation on TEN FPSO is to be located in Offshore Ghana, Africa.

Scope of work includes :

  • Design of Supply Material
  • Construction & Assembly Work
  • Painting Work
  • Architectural Work
  • Installation of Available free issue equipment
  • Interconnecting cabling
  • F&G System
  • Testing & Commissioning
  • MC and Documentation
The total weight of prefabricate electrical house’s are 497Tons Project in progres contruction with curent cummulative manhours spents up to end of Jan 2014 = 1187 manhours WITHOUT LOST TIME INJURIES